We’re finally seeing signs of spring at Minto Southshore. We made steady progress during the winter, but now that the weather is warmer, we’re looking forward to putting a little spring in our step and seeing even more progress at the site. Here’s an update on what we’ve been up to lately.

Concrete Formwork

We’re continuing the concrete work for the front entry porches at blocks 6 and 7 and this will continue for the next couple of weeks.

Underground Garage Work

Enbridge is currently connecting the main gas line connections to block 5, 6, and 7. We’re also continuing the mechanical and electrical equipment finishing and painting the garages in block 6 and 7.

In the upcoming weeks, ceiling insulation will start in block 1 and 2 and we’ll start the installation of the garage signage, sprinkler system and garage lockers.

 

Screen Shot 2014-05-02 at 4.00.17 PM

Excavation, site servicing and landscaping 

The site servicing work is 95% complete and we’ve also completed the stone retaining wall at the garage entrance. In the next few weeks we’ll start the hardscape work along 24th street at block 1 and 2.

Townhouses

We’re making great progress with the townhouses. On block 1, we’ve finished installing the hardware and have moved on to the appliance delivery and installation. Over at block 2, we’re installing the kitchen countertops, mirrors and glass shower.

Screen Shot 2014-05-02 at 4.00.09 PM

Meanwhile on block 3, the tile installation is 90% complete, the kitchen installation is 75% complete and the trim carpentry is in progress along with the painting and installation of the mechanical equipment and electrical and HVAC finishing.

On block 4 the drywall installation is 60% complete while over on block 5, the drywall installation is just starting. On block 6, the drywall fire separation installation is in progress and is also almost complete on block 7.

Southshore is sold out but you can check out our newest project Minto Longbranch which is just a few minutes away and is one of the top 10 developments in the GTA.

Leave a Reply

Your email address will not be published. Required fields are marked *

* Copy This Password *

* Type Or Paste Password Here *